Trithiya Serenity, Grant Road

by Sach Geo Resources Private Limited · Grant Road, Mumbai 400007 · Map

Launched
Jun 20263 yrs 6 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
2 of 239% · 0 in Jul 2026
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
15
3 BHK
8
Total units
23
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation23%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 23%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 23%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
23%0%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Trithiya Serenity by Sach Geo Resources Private Limited is a 23-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in June 2026 with possession due in December 2029. 2 units booked out of total 23 units. Work on the concrete structure (RCC) has not started.

Read full summary

Trithiya Serenity is a BMC-sanctioned project by Sach Geo Resources Private Limited in Grant Road, Mumbai 400007, registered with MahaRERA as PR1170002600740. It was launched in June 2026. It has 23 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 23% complete, structure (RCC) not started, final finishes not started.

2 units booked out of total 23 units (9%). Since the July 2026 update, 2 more units have been booked.