San Petros Residency, Dadar West

by San Petros Properties · Dadar West, Mumbai 400028 · Map

Launched
Jun 20261 yr promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
35%Mid-construction
Booked
0 of 120%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
10
Other units
2
Total units
12
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 35%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

San Petros Residency by San Petros Properties is a 12-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in June 2026 with possession due in June 2027. 0 units booked out of total 12 units. The concrete structure (RCC) is 35% complete.

Read full summary

San Petros Residency is a BMC-sanctioned project by San Petros Properties in Dadar West, Mumbai 400028, registered with MahaRERA as PR1170002600803. It was launched in June 2026. It has 12 units in 1 building: 10 homes (1 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

0 units booked out of total 12 units (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 35%.