Skip to main content

Miami By Purva, Cumballa Hill

by Puravankara Limited · Cumballa Hill, Mumbai 400026 · Map

Launched
Jun 20266 yrs promised
Possession (MahaRERA)
Jun 2032Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 190% · 26 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 19 units

Rehab26 units for existing members

Total 45 units. Rehab units are not for sale.

Project facts

3 BHK
9
4 BHK
34
5+ BHK
2
Total units
45
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
19
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Miami By Purva by Puravankara Limited is a 45-unit SRA-sanctioned project in Cumballa Hill, Mumbai 400026, launched in June 2026 with possession due in June 2032. 0 units booked out of 19 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Miami By Purva is an SRA-sanctioned project by Puravankara Limited in Cumballa Hill, Mumbai 400026, registered with MahaRERA as PR1170002600857. It was launched in June 2026. It has 45 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 45 units, 19 are for sale and 26 are rehab units for existing members.

Its registered possession date is June 2032, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 19 units for sale (0%).

Puravankara's track record in Mumbai

MahaRERA projects registered 2021–2026 in Mumbai

Projects registered with MahaRERA7
Total units across these projects903
Completed without extending the possession date0
Completed after an extension0
Lapsed0
Under construction7
Possession date extended on the builder's application0
Typical time from launch to 100% structure4 years 9 months
MahaRERA complaints (filed by or against the builder), all Puravankara projects3 (2 of 7 projects)