Veer Square Dadar, Dadar West

by P D Associates · Dadar West, Mumbai 400028 · Map

Launched
Jul 20262 yrs 8 mths originally promised
Possession (MahaRERA)
Jul 2029Extended by 4 mths
Concrete structure
34%Mid-construction
Booked (free sale)
12 of 8414% · 143 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 84 units

Rehab143 units for existing members

Land-owner share13 units, not for sale

Total 240 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
16
1 BHK
2
Other units
222
Total units
240
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
84
Rehab units
143
Land-owner share (not for sale)
13
Reserved units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)34%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%34%0%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs 2 mths
Possession date extendedBy 4 mths0 of 5
Possession date (MahaRERA)Jul 2029Dec 2029
Concrete structure (RCC)34%0%
Units booked (free sale)14%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Veer Square Dadar by P D Associates is a 240-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in July 2026 with possession due in July 2029. 12 units booked out of 84 units for sale. The concrete structure (RCC) is 34% complete.

Read full summary

Veer Square Dadar is a BMC-sanctioned project by P D Associates in Dadar West, Mumbai 400028, registered with MahaRERA as PR1170002601320. It was launched in July 2026. It has 240 units in 2 buildings: 18 homes (1 RK and 1 BHK) and 222 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 240 units, 84 are for sale, 143 are rehab units for existing members and 13 are the land-owner's share, not for sale.

Its registered possession date is July 2029, extended by 4 months from the original March 2029. Construction: excavation complete, structure (RCC) 34% complete, final finishes not started.

12 units booked out of 84 units for sale (14%).