Sugee Vrundavan, Mahim

by Sugee Developers Private Limited · Mahim, Mumbai 400016 · Map

Launched
Aug 20263 yrs 4 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
1 of 432% · 52 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 43 units

Rehab52 units for existing members

Total 95 units. Rehab units are not for sale.

Project facts

1 BHK
28
2 BHK
39
3 BHK
28
Total units
95
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
43
Rehab units
52

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation85%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
85%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sugee Vrundavan by Sugee Developers Private Limited is a 95-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in August 2026 with possession due in December 2029. 1 unit booked out of 43 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Sugee Vrundavan is a BMC-sanctioned project by Sugee Developers Private Limited in Mahim, Mumbai 400016, registered with MahaRERA as PR1170002601623. It was launched in August 2026. It has 95 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 95 units, 43 are for sale and 52 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 85% complete, structure (RCC) not started, final finishes not started.

1 unit booked out of 43 units for sale (2%).