11 Astoria, Mumbai Central

by Ibrahim Jusab Sopariwala & Others · Mumbai Central, Mumbai 400008 · Map

Launched
Sep 20264 yrs 3 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 130% · 159 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 13 units

Rehab159 units for existing members

Total 172 units. Rehab units are not for sale.

Project facts

1 BHK
60
2 BHK
2
Other units
110
Total units
172
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
159

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

11 Astoria by Ibrahim Jusab Sopariwala & Others is a 172-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in September 2026 with possession due in December 2030. 0 units booked out of 13 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

11 Astoria is a BMC-sanctioned project by Ibrahim Jusab Sopariwala & Others in Mumbai Central, Mumbai 400008, registered with MahaRERA as PR1170002601734. It was launched in September 2026. It has 172 units in 1 building: 62 homes (1 and 2 BHK) and 110 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 172 units, 13 are for sale and 159 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation 70% complete, structure (RCC) not started, final finishes not started.

0 units booked out of 13 units for sale (0%).