by Aadi Shikhar LLP · Sion, Mumbai 400022 · Map

Launched
Apr 20261 yr 8 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
12%Mid-construction
Booked (free sale)
0 of 30% · 10 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 3 units

Rehab10 units for existing members

Total 13 units. Rehab units are not for sale.

Project facts

1 BHK
2
3 BHK
11
Total units
13
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
3
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)12%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 24%Oct 2026: Concrete structure (RCC) 12%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 12%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%12%0%0
100%24%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aadi Arpan NX by Aadi Shikhar LLP is a 13-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in April 2026 with possession due in December 2027. 0 units booked out of 3 units for sale. The concrete structure (RCC) is 12% complete.

Read full summary

Aadi Arpan NX is a BMC-sanctioned project by Aadi Shikhar LLP in Sion, Mumbai 400022, registered with MahaRERA as PR1171012600106. It was launched in April 2026. It has 13 units in 1 building, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 13 units, 3 are for sale and 10 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 12% complete, final finishes not started.

0 units booked out of 3 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 24% to 12%.