Aadi Arpan NX, Sion
by Aadi Shikhar LLP · Sion, Mumbai 400022 · Map
- Launched
- Apr 20261 yr 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 12%Mid-construction
- Booked (free sale)
- 0 of 30% · 10 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 3 units
Rehab10 units for existing members
Total 13 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 2
- 3 BHK
- 11
- Total units
- 13
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 3
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 12% | 0% | 0 | |
| 100% | 24% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aadi Arpan NX by Aadi Shikhar LLP is a 13-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in April 2026 with possession due in December 2027. 0 units booked out of 3 units for sale. The concrete structure (RCC) is 12% complete.
Read full summary
Aadi Arpan NX is a BMC-sanctioned project by Aadi Shikhar LLP in Sion, Mumbai 400022, registered with MahaRERA as PR1171012600106. It was launched in April 2026. It has 13 units in 1 building, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 13 units, 3 are for sale and 10 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 12% complete, final finishes not started.
0 units booked out of 3 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 24% to 12%.