Supreme Boulevard Chembur, Mankhurd
by Supreme Sky High Private Limited · Mankhurd, Mumbai 400088 · Map
- Launched
- Oct 2024First of 2 phases
- Possession (MahaRERA)
- Mar 2029 – Dec 2029Not extended
- Concrete structure
- 61%Weighted across 2 phases
- Booked
- 116 of 11898%
- Buildings
- 24.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 36
- 3 BHK
- 73
- 4 BHK
- 9
- Total units
- 118
- Buildings
- 2
- Land
- 4.9 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Supreme Boulevard Chembur Wing B Mid-construction | PR1180002400026 | 89 | 66% | 100% | |
| Supreme Boulevard Chembur Wing A Mid-construction | P51800079148 | 29 | 44% | 93% |
Show updates by phase
Supreme Boulevard Chembur Wing B (PR1180002400026)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 66% | 1% | 89 | |
| 100% | 33% | 0% | 87 | |
| 100% | 5% | 0% | 89 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Supreme Boulevard Chembur Wing A (P51800079148)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 44% | 1% | 27 | |
| 100% | 0% | 0% | 29 | |
| 100% | 0% | 0% | 29 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 4 similar projects in PIN 400088
Projects with 50–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 3 yrs 2 mths |
| Possession date extended | No | 2 of 4 |
| Possession date (MahaRERA) | Mar 2029 – Dec 2029 | Sep 2027 |
| Concrete structure (RCC) | 61% | 96% |
| Units booked | 98% | 37% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Misty Heights, Mankhurd
- Anuvidnyan Nagar Co-Op. Housing Society Ltd, Mankhurd
- Godrej Sky Terraces, Mankhurd
- Akshar Amar Mansion, Mankhurd
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Misty Heights | March 2024 | December 2027 | 5% | 7 units booked out of 73 units for sale |
| Anuvidnyan Nagar Co-Op. Housing Society Ltd | December 2023 | June 2027 | 91% | 10 units booked out of 110 units for sale |
| Godrej Sky Terraces | December 2023 | March 2029 | 100% | 70 units booked out of total 76 units |
| Akshar Amar Mansion | October 2023 | March 2027 | 100% | 21 units booked out of 33 units for sale |
About this project
Supreme Boulevard Chembur by Supreme Sky High Private Limited is a 118-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, registered with MahaRERA in 2 phases, with possession dates from March 2029 to December 2029. 116 units booked out of total 118 units. The concrete structure (RCC) is 61% complete.
Read full summary
Supreme Boulevard Chembur is a BMC-sanctioned project by Supreme Sky High Private Limited in Mankhurd, Mumbai 400088, registered with MahaRERA as 2 phases (PR1180002400026, P51800079148). The first phase was launched in October 2024. Together the phases have 118 units in 2 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from March 2029 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 61% complete and final finishes 1% complete. Neither phase has its structure complete.
116 units booked out of total 118 units (98%).