Nehru Nagar Shivalaya Chsl, Kurla East

by Citiline Constructions LLP · Kurla East, Mumbai 400024 · Map

Launched
Oct 20243 yrs 8 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation35%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 35%Dec 2025: Excavation 35%Jul 2026: Excavation 35%Oct 2026: Excavation 35%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 35%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
35%0%0%–
35%0%0%–
35%0%0%–
35%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nehru Nagar Shivalaya Chsl by Citiline Constructions LLP is a MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in October 2024 with possession due in June 2028. Work on the concrete structure (RCC) has not started.

Read full summary

Nehru Nagar Shivalaya Chsl is a MHADA-sanctioned project by Citiline Constructions LLP in Kurla East, Mumbai 400024, registered with MahaRERA as PR1180002400030. It was launched in October 2024. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation 35% complete, structure (RCC) not started, final finishes not started.