Dps Sanctum, Dahisar
Ready to move
by Sanctum Infratech Private Limited · Dahisar, Mumbai 400068 · Map
- Launched
- Oct 20242 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 26 of 3184% · 37 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale26 booked out of 31 units
Rehab37 units for existing members
Total 68 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 49
- 3 BHK
- 2
- Total units
- 68
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 37
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 26 | |
| 100% | 78% | 0% | 11 | |
| 0% | 0% | 0% | 12 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400068
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 3 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2027 |
| Concrete structure (RCC) | 100% | 32% |
| Units booked (free sale) | 84% | 63% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shiv Guru Tower, Dahisar
- Rajanigandha Chsl, Dahisar
- Krishnaraj Buildcon New Suryadarshan Co Op Hsg. Soc, Dahisar
- Nandanvan Mohan CHSL, Dahisar
- Skymont Siddhi, Dahisar
- Mpr Varsha, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shiv Guru Tower | November 2024 | December 2027 | 20% | 16 units booked out of 28 units for sale |
| Rajanigandha Chsl | December 2024 | June 2027 | 75% | 17 units booked out of 25 units for sale |
| Krishnaraj Buildcon New Suryadarshan Co Op Hsg. Soc | August 2024 | December 2027 | 30% | 8 units booked out of 20 units for sale |
| Nandanvan Mohan CHSL | June 2024 | December 2027 | 11% | 29 units booked out of 36 units for sale |
| Skymont Siddhi | March 2025 | December 2029 | 35% | 45 units booked out of 54 units for sale |
| Mpr Varsha | March 2025 | October 2027 | 100% | 6 units booked out of 21 units for sale |
About this project
Dps Sanctum by Sanctum Infratech Private Limited is a 68-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in October 2024 with possession due in December 2026. 26 units booked out of 31 units for sale. The concrete structure (RCC) is complete.
Read full summary
Dps Sanctum is a BMC-sanctioned project by Sanctum Infratech Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as PR1180002400063. It was launched in October 2024. It has 68 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 68 units, 31 are for sale and 37 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
26 units booked out of 31 units for sale (84%). Since the July 2026 update, 15 more units have been booked and the reported concrete structure (RCC) has gone from 78% to 100%.