Palace Powai, Bhandup East

by Yug Developers · Bhandup East, Mumbai 400042 · Map

Launched
Jul 20253 yrs 2 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
45%Mid-construction
Booked (free sale)
1 of 157% · 20 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 15 units

Rehab20 units for existing members

Total 35 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
2
2 BHK
17
3 BHK
15
Total units
35
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 45%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%1
100%25%0%1
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400042

Projects with 10–70 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400042
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths3 yrs 7 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Sep 2028Oct 2029
Concrete structure (RCC)45%0%
Units booked (free sale)7%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Palace Powai by Yug Developers is a 35-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in July 2025 with possession due in September 2028. 1 unit booked out of 15 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Palace Powai is a BMC-sanctioned project by Yug Developers in Bhandup East, Mumbai 400042, registered with MahaRERA as PR1180002500278. It was launched in July 2025. It has 35 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 15 are for sale and 20 are rehab units for existing members.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

1 unit booked out of 15 units for sale (7%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 25% to 45%.