Optimus, Borivali West
by Panchnaad Developers · Borivali West, Mumbai 400103 · Map
- Launched
- Jul 20251 yr 5 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 45%Mid-construction
- Booked (free sale)
- 7 of 1547% · 12 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 15 units
Rehab12 units for existing members
Total 27 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 12
- 2 BHK
- 7
- Other units
- 5
- Total units
- 27
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 15
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 7 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400103
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 5 mths | 2 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Jul 2028 |
| Concrete structure (RCC) | 45% | 12% |
| Units booked (free sale) | 47% | 29% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Concepta Chsl, Borivali West
- Redevelopment Of Sbi Emp Navjeevan Chsl, Borivali West
- Empire Preston, Borivali West
- Ave Maria, Borivali West
- Hariko Brahma, Borivali West
- Questend Co Op Housing Society Ltd, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Concepta Chsl | August 2025 | December 2027 | 60% | 2 units booked out of 9 units for sale |
| Redevelopment Of Sbi Emp Navjeevan Chsl | August 2025 | July 2028 | 56% | 6 units booked out of 19 units for sale |
| Empire Preston | October 2025 | July 2028 | 25% | 1 unit booked out of 11 units for sale |
| Ave Maria | December 2025 | March 2029 | 0% | 9 units booked out of 31 units for sale |
| Hariko Brahma | January 2025 | December 2029 | 0% | 10 units booked out of total 23 units |
| Questend Co Op Housing Society Ltd | January 2025 | December 2027 | 0% | – |
About this project
Optimus by Panchnaad Developers is a 27-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in July 2025 with possession due in December 2026. 7 units booked out of 15 units for sale. The concrete structure (RCC) is 45% complete.
Read full summary
Optimus is a BMC-sanctioned project by Panchnaad Developers in Borivali West, Mumbai 400103, registered with MahaRERA as PR1180002500322. It was launched in July 2025. It has 27 units in 1 building: 22 homes (1 RK, 1 BHK and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 15 are for sale and 12 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.
7 units booked out of 15 units for sale (47%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 45%.