Skip to main content

Optimus, Borivali West

by Panchnaad Developers · Borivali West, Mumbai 400103 · Map

Launched
Jul 20251 yr 5 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
45%Mid-construction
Booked (free sale)
7 of 1547% · 12 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 15 units

Rehab12 units for existing members

Total 27 units. Rehab units are not for sale.

Project facts

1 RK
3
1 BHK
12
2 BHK
7
Other units
5
Total units
27
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 45%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%7
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400103

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 5 mths2 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2026Jul 2028
Concrete structure (RCC)45%12%
Units booked (free sale)47%29%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Optimus by Panchnaad Developers is a 27-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in July 2025 with possession due in December 2026. 7 units booked out of 15 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Optimus is a BMC-sanctioned project by Panchnaad Developers in Borivali West, Mumbai 400103, registered with MahaRERA as PR1180002500322. It was launched in July 2025. It has 27 units in 1 building: 22 homes (1 RK, 1 BHK and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 15 are for sale and 12 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

7 units booked out of 15 units for sale (47%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 45%.