Sai Siddhi Residency, Andheri East
by Sa Developers · Andheri East, Mumbai 400069 · Map
- Launched
- Jul 20253 yrs 10 mths promised
- Possession (MahaRERA)
- May 2029Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 8 of 1650% · 16 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 16 units
Rehab16 units for existing members
Total 32 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 13
- 3 BHK
- 15
- Other units
- 1
- Total units
- 32
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 16
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 8 | |
| 100% | 45% | 0% | 6 | |
| 100% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Sai Siddhi Residency by Sa Developers is a 32-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in July 2025 with possession due in May 2029. 8 units booked out of 16 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sai Siddhi Residency is a BMC-sanctioned project by Sa Developers in Andheri East, Mumbai 400069, registered with MahaRERA as PR1180002500341. It was launched in July 2025. It has 32 units in 1 building: 31 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 16 are for sale and 16 are rehab units for existing members.
Its registered possession date is May 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
8 units booked out of 16 units for sale (50%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 45% to 100%.