Trinity Towers, Santacruz East
by Jet Speed Realtors Private Limited · Santacruz East, Mumbai 400055 · Map
- Launched
- Aug 20253 yrs 7 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 21 of 6035% · 80 rehab units
- Buildings
- 30.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 60 units
Rehab80 units for existing members
Total 140 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 30
- 2 BHK
- 66
- 3 BHK
- 32
- 4 BHK
- 6
- Other units
- 6
- Total units
- 140
- Buildings
- 3
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 60
- Rehab units
- 80
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 77% | 0% | 0% | 21 | |
| 77% | 0% | 0% | 7 | |
| 0% | 0% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
About this project
Trinity Towers by Jet Speed Realtors Private Limited is a 140-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2025 with possession due in March 2029. 21 units booked out of 60 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Trinity Towers is a BMC-sanctioned project by Jet Speed Realtors Private Limited in Santacruz East, Mumbai 400055, registered with MahaRERA as PR1180002500480. It was launched in August 2025. It has 140 units in 3 buildings: 134 homes (1, 2, 3 and 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 140 units, 60 are for sale and 80 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation 77% complete, structure (RCC) not started, final finishes not started.
21 units booked out of 60 units for sale (35%). Since the July 2026 update, 14 more units have been booked.