Aquina, Andheri East

by Rajiv Construction Company Developers · Andheri East, Mumbai 400059 · Map

Launched
Aug 20252 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked
71 of 8287% · 62 in Jul 2026
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
20
2 BHK
51
3 BHK
11
Total units
82
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%71
100%0%0%62
100%0%0%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aquina by Rajiv Construction Company Developers is an 82-unit SRA-sanctioned project in Andheri East, Mumbai 400059, launched in August 2025 with possession due in December 2027. 71 units booked out of total 82 units. Work on the concrete structure (RCC) has not started.

Read full summary

Aquina is an SRA-sanctioned project by Rajiv Construction Company Developers in Andheri East, Mumbai 400059, registered with MahaRERA as PR1180002500577. It was launched in August 2025. It has 82 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

71 units booked out of total 82 units (87%). Since the July 2026 update, 9 more units have been booked.