Ameya Residency, Sion

by Ameya Realtors Private Limited · Sion, Mumbai 400022 · Map

Launched
Aug 20254 yrs 4 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
20%Mid-construction
Booked (free sale)
19 of 3850% · 57 rehab units
Buildings
20.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale19 booked out of 38 units

Rehab57 units for existing members

Total 95 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
5
2 BHK
70
3 BHK
19
Total units
95
Buildings
2
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Free-sale units
38
Rehab units
57

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)20%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 50%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 20%Oct 2026: Concrete structure (RCC) 20%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 20%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%19
100%20%0%19
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ameya Residency by Ameya Realtors Private Limited is a 95-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in August 2025 with possession due in December 2029. 19 units booked out of 38 units for sale. The concrete structure (RCC) is 20% complete.

Read full summary

Ameya Residency is a BMC-sanctioned project by Ameya Realtors Private Limited in Sion, Mumbai 400022, registered with MahaRERA as PR1180002500624. It was launched in August 2025. It has 95 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 95 units, 38 are for sale and 57 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

19 units booked out of 38 units for sale (50%).