Skip to main content

Puneet Allure, Vikhroli

by Puneet Edifice Pvt Ltd · Vikhroli, Mumbai 400083 · Map

Launched
Sep 20254 yrs 3 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
1%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)1%
Finishes, lifts and services1%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 1%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 1%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 1%Dec 2025: Final finishes 1%Jul 2026: Final finishes 0%Oct 2026: Final finishes 1%Excavation 100%Concrete structure (RCC) 1%Final finishes 1%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%1%1%–
100%0%0%–
1%1%1%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Puneet Allure by Puneet Edifice Pvt Ltd is a MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in September 2025 with possession due in December 2029. The concrete structure (RCC) is 1% complete.

Read full summary

Puneet Allure is a MHADA-sanctioned project by Puneet Edifice Pvt Ltd in Vikhroli, Mumbai 400083, registered with MahaRERA as PR1180002500687. It was launched in September 2025. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 1% complete, final finishes 1% complete.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 1%.