Choice Ambe Shraddha, Ghatkopar East
by Choice Builders And Developers LLP · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Sep 20253 yrs promised
- Possession (MahaRERA)
- Sep 2028Not extended
- Concrete structure
- 93%Mid-construction
- Booked (free sale)
- 64 of 9567% · 30 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale64 booked out of 95 units
Rehab30 units for existing members
Total 125 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 63
- 2 BHK
- 47
- 3 BHK
- 15
- Total units
- 125
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 95
- Rehab units
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 93% | 0% | 64 | |
| 100% | 6% | 0% | 40 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Choice Ambe Shraddha by Choice Builders And Developers LLP is a 125-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in September 2025 with possession due in September 2028. 64 units booked out of 95 units for sale. The concrete structure (RCC) is 93% complete.
Read full summary
Choice Ambe Shraddha is a MHADA-sanctioned project by Choice Builders And Developers LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as PR1180002500720. It was launched in September 2025. It has 125 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 125 units, 95 are for sale and 30 are rehab units for existing members.
Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 93% complete, final finishes not started.
64 units booked out of 95 units for sale (67%). Since the July 2026 update, 24 more units have been booked and the reported concrete structure (RCC) has gone from 6% to 93%.