Chandra Logassa, Andheri West
by Amaan Gold Leaf Developers · Andheri West, Mumbai 400058 · Map
- Launched
- Sep 20252 yrs 11 mths promised
- Possession (MahaRERA)
- Aug 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 53 of 8960% · 16 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale53 booked out of 89 units
Rehab16 units for existing members
Total 105 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 66
- 2 BHK
- 34
- Other units
- 5
- Total units
- 105
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 89
- Rehab units
- 16
- Reserved units
- 52
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 53 | |
| 50% | 0% | 0% | 52 | |
| 0% | 0% | 0% | 52 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400058
Projects with 50–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 3 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Aug 2028 | Dec 2028 |
| Concrete structure (RCC) | 0% | 75% |
| Units booked (free sale) | 60% | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Navkar Elegance, Andheri West
- Navkar Palace, Andheri West
- Mesacon Harmony, Andheri West
- Bhoomi Amogh, Andheri West
- Mk Gloria, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Navkar Elegance | October 2025 | August 2028 | 100% | 15 units booked out of 27 units for sale |
| Navkar Palace | July 2025 | October 2028 | 100% | 26 units booked out of 39 units for sale |
| Mesacon Harmony | December 2025 | March 2029 | 0% | 13 units booked out of 52 units for sale |
| Bhoomi Amogh | January 2026 | December 2029 | 0% | 43 units booked out of 61 units for sale |
| Mk Gloria | March 2026 | December 2028 | 75% | 34 units booked out of 57 units for sale |
About this project
Chandra Logassa by Amaan Gold Leaf Developers is a 105-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in September 2025 with possession due in August 2028. 53 units booked out of 89 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Chandra Logassa is an SRA-sanctioned project by Amaan Gold Leaf Developers in Andheri West, Mumbai 400058, registered with MahaRERA as PR1180002501009. It was launched in September 2025. It has 105 units in 2 buildings: 100 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 105 units, 89 are for sale and 16 are rehab units for existing members.
Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
53 units booked out of 89 units for sale (60%). Since the July 2026 update, 1 more unit has been booked.