Aurora, Ghatkopar East
by Yashodanand Developers · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Oct 20252 yrs 9 mths promised
- Possession (MahaRERA)
- Jul 2028Not extended
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
About this project
Aurora by Yashodanand Developers is a BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in October 2025 with possession due in July 2028. Work on the concrete structure (RCC) has not started.
Read full summary
Aurora is a BMC-sanctioned project by Yashodanand Developers in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PR1180002501146. It was launched in October 2025. Its MahaRERA status is Active.
Its registered possession date is July 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.