Paul Chamber, Bhandup West

by Sudhanshu Infrastructures Private Limited · Bhandup West, Mumbai 400078 · Map

Launched
Oct 20251 yr 10 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
12 of 1580% · 24 rehab units
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 15 units

Rehab24 units for existing members

Total 39 units. Rehab units are not for sale.

Project facts

1 BHK
39
Total units
39
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%12
100%0%0%12
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400078

Projects with 10–80 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 10 mths3 yrs 9 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Aug 2027Dec 2028
Concrete structure (RCC)0%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Paul Chamber by Sudhanshu Infrastructures Private Limited is a 39-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in October 2025 with possession due in August 2027. 12 units booked out of 15 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Paul Chamber is a BMC-sanctioned project by Sudhanshu Infrastructures Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as PR1180002501359. It was launched in October 2025. It has 39 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 39 units, 15 are for sale and 24 are rehab units for existing members.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

12 units booked out of 15 units for sale (80%).