Roswalt Shatataraka (Unit A) CHSL, Andheri West
by Roswalt Realty Private Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Oct 20252 yrs 11 mths promised
- Possession (MahaRERA)
- Sep 2028Not extended
- Concrete structure
- 18%Mid-construction
- Booked (free sale)
- 9 of 2931% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 29 units
Rehab20 units for existing members
Total 49 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 6
- 2 BHK
- 35
- 3 BHK
- 6
- Other units
- 2
- Total units
- 49
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 29
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 0% | 9 | |
| 100% | 0% | 0% | 4 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400053
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Sep 2028 | Sep 2029 |
| Concrete structure (RCC) | 18% | 14% |
| Units booked (free sale) | 31% | 53% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Linkbay Residences Phase II Wing B, Andheri West
- Mesacon Magic Carpet, Andheri West
- The Redevelopment Of You And I Chsl, Andheri West
- Signia, Andheri West
- Khandelwal Tattva, Andheri West
- Redevelopment Of Daulatrao Desai Nagar Chsl, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Linkbay Residences Phase II Wing B | October 2025 | June 2030 | 19% | 88 units booked out of total 88 units |
| Mesacon Magic Carpet | November 2025 | July 2028 | 23% | 18 units booked out of 27 units for sale |
| The Redevelopment Of You And I Chsl | August 2025 | February 2029 | 8% | 9 units booked out of 11 units for sale |
| Signia | December 2025 | March 2030 | 0% | 1 unit booked out of 8 units for sale |
| Khandelwal Tattva | December 2025 | December 2030 | 0% | 0 units booked out of 7 units for sale |
| Redevelopment Of Daulatrao Desai Nagar Chsl | July 2025 | November 2028 | 26% | 6 units booked out of 15 units for sale |
About this project
Roswalt Shatataraka (Unit A) CHSL by Roswalt Realty Private Limited is a 49-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in October 2025 with possession due in September 2028. 9 units booked out of 29 units for sale. The concrete structure (RCC) is 18% complete.
Read full summary
Roswalt Shatataraka (Unit A) CHSL is an SRA-sanctioned project by Roswalt Realty Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002501378. It was launched in October 2025. It has 49 units in 1 building: 47 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 29 are for sale and 20 are rehab units for existing members.
Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 18% complete, final finishes not started.
9 units booked out of 29 units for sale (31%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 18%.