Velcon Pride, Chembur

by Velcon Realtors · Chembur, Mumbai 400089 · Map

Launched
Dec 20254 yrs promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
75%Mid-construction
Booked (free sale)
4 of 1233% · 18 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 12 units

Rehab18 units for existing members

Total 30 units. Rehab units are not for sale.

Project facts

2 BHK
12
3 BHK
18
Total units
30
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 75%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%4
100%0%0%1
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Velcon Pride by Velcon Realtors is a 30-unit BMC-sanctioned project in Chembur, Mumbai 400089, launched in December 2025 with possession due in December 2029. 4 units booked out of 12 units for sale. The concrete structure (RCC) is 75% complete.

Read full summary

Velcon Pride is a BMC-sanctioned project by Velcon Realtors in Chembur, Mumbai 400089, registered with MahaRERA as PR1180002501712. It was launched in December 2025. It has 30 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 12 are for sale and 18 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.

4 units booked out of 12 units for sale (33%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 75%.