Crystal Prime Meridian, Ghatkopar East
by Aryamaan Developers Private Limited · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jan 20264 yrs 10 mths originally promised
- Possession (MahaRERA)
- Nov 2032Extended by 2 yrs
- Concrete structure
- 0%Early stage
- Booked
- 85 of 47318% · 0 in Jul 2026
- Buildings
- 111.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 276
- 2 BHK
- 197
- Total units
- 473
- Buildings
- 1
- Land
- 11.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 85 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Crystal Prime Meridian by Aryamaan Developers Private Limited is a 473-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in January 2026 with possession due in November 2032. 85 units booked out of total 473 units. Work on the concrete structure (RCC) has not started.
Read full summary
Crystal Prime Meridian is an SRA-sanctioned project by Aryamaan Developers Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PR1180002502173. It was launched in January 2026. It has 473 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is November 2032, extended by 2 years from the original November 2030. Construction: excavation not started, structure (RCC) not started, final finishes not started.
85 units booked out of total 473 units (18%). Since the July 2026 update, 85 more units have been booked.