Tescon Canvase, Chembur

by Tescongreen Private Limited · Chembur, Mumbai 400074 · Map

Launched
Jan 20263 yrs 11 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 70%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Tescon Canvase by Tescongreen Private Limited is a BMC-sanctioned project in Chembur, Mumbai 400074, launched in January 2026 with possession due in December 2029. Work on the concrete structure (RCC) has not started.

Read full summary

Tescon Canvase is a BMC-sanctioned project by Tescongreen Private Limited in Chembur, Mumbai 400074, registered with MahaRERA as PR1180002502218. It was launched in January 2026. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 70% complete, structure (RCC) not started, final finishes not started.