Skip to main content

Sumit Bhakti, Santacruz East

by Sumit Pragati Ventures LLP · Santacruz East, Mumbai 400055 · Map

Launched
Feb 20262 yrs 1 mth promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
4 of 4010% · 68 rehab units
Buildings
60.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 40 units

Rehab68 units for existing members

Total 108 units. Rehab units are not for sale.

Project facts

1 BHK
15
2 BHK
89
3 BHK
4
Total units
108
Buildings
6
Land
0.9 acres
Phases
1
MahaRERA complaints
0
Free-sale units
40
Rehab units
68

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation83%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 5%Oct 2026: Excavation 83%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 83%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
83%0%0%4
5%0%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sumit Bhakti by Sumit Pragati Ventures LLP is a 108-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in February 2026 with possession due in March 2028. 4 units booked out of 40 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Sumit Bhakti is a BMC-sanctioned project by Sumit Pragati Ventures LLP in Santacruz East, Mumbai 400055, registered with MahaRERA as PR1180002502307. It was launched in February 2026. It has 108 units in 6 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 108 units, 40 are for sale and 68 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation 83% complete, structure (RCC) not started, final finishes not started.

4 units booked out of 40 units for sale (10%). Since the July 2026 update, 2 more units have been booked.