Skip to main content

Galaxy Aura, Ghatkopar East

by Rudra Techno Construction Homes LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Mar 20263 yrs 9 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
3 of 1030% · 33 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 10 units

Rehab33 units for existing members

Total 43 units. Rehab units are not for sale.

Project facts

1 BHK
43
Total units
43
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
10
Rehab units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 50%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%3
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Dec 2029
Concrete structure (RCC)0%0%
Units booked (free sale)30%2%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Galaxy Aura by Rudra Techno Construction Homes LLP is a 43-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in March 2026 with possession due in December 2029. 3 units booked out of 10 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Galaxy Aura is a BMC-sanctioned project by Rudra Techno Construction Homes LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PR1180002502541. It was launched in March 2026. It has 43 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 43 units, 10 are for sale and 33 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

3 units booked out of 10 units for sale (30%). Since the July 2026 update, 3 more units have been booked.