Dena Sadichchha Co Operative Housing Society Limited, Borivali West
by Dena Sadichchha Cooperative Housing Society Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Mar 20262 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 2 of 1811% · 10 rehab units
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 18 units
Rehab10 units for existing members
Total 28 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 15
- 2 BHK
- 13
- Total units
- 28
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 2 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Mar 2029 |
| Concrete structure (RCC) | 0% | 32% |
| Units booked (free sale) | 11% | 4% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- RC 92 - Redevelopment of New Link View CHSL, Borivali West
- Vardhaman, Borivali West
- Acres Aarambh, Borivali West
- Pooja Co-Operative Housing Society Limited, Borivali West
- Vanita Niketan Co Operative Housing Society, Borivali West
- Rohom Radiance, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| RC 92 - Redevelopment of New Link View CHSL | March 2026 | June 2029 | 29% | 5 units booked out of 10 units for sale |
| Vardhaman | March 2026 | December 2028 | 35% | 0 units booked out of 7 units for sale |
| Acres Aarambh | March 2026 | April 2028 | 60% | 0 units booked out of 10 units for sale |
| Pooja Co-Operative Housing Society Limited | February 2026 | October 2029 | 0% | 1 unit booked out of 12 units for sale |
| Vanita Niketan Co Operative Housing Society | February 2026 | December 2028 | 0% | 0 units booked out of 3 units for sale |
| Rohom Radiance | February 2026 | September 2029 | 90% | 10 units booked out of total 42 units |
About this project
Dena Sadichchha Co Operative Housing Society Limited by Dena Sadichchha Cooperative Housing Society Limited is a 28-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in March 2026 with possession due in December 2028. 2 units booked out of 18 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Dena Sadichchha Co Operative Housing Society Limited is a BMC-sanctioned project by Dena Sadichchha Cooperative Housing Society Limited in Borivali West, Mumbai 400092, registered with MahaRERA as PR1180002502792. It was launched in March 2026. It has 28 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 18 are for sale and 10 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
2 units booked out of 18 units for sale (11%). Since the July 2026 update, 2 more units have been booked.