Skip to main content

Virgo, Kandivali West

by Virgo Infraspace Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Mar 20263 yrs promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Virgo by Virgo Infraspace Private Limited is a BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2026 with possession due in March 2029. Work on the concrete structure (RCC) has not started.

Read full summary

Virgo is a BMC-sanctioned project by Virgo Infraspace Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as PR1180002502876. It was launched in March 2026. Its MahaRERA status is Active.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.