Govind Dham, Santacruz East

by Ambrosial Developers Private Limited · Santacruz East, Mumbai 400055 · Map

Launched
Mar 20265 yrs promised
Possession (MahaRERA)
Mar 2031Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 280% · 15 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 28 units

Rehab15 units for existing members

Land-owner share3 units, not for sale

Total 46 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
12
2 BHK
21
3 BHK
11
Other units
2
Total units
46
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
15
Land-owner share (not for sale)
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 50%Oct 2026: Excavation 50%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%0
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400055

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400055
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs5 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2031Dec 2031
Concrete structure (RCC)0%0%
Units booked (free sale)0%55%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Govind Dham by Ambrosial Developers Private Limited is a 46-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in March 2026 with possession due in March 2031. 0 units booked out of 28 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Govind Dham is a BMC-sanctioned project by Ambrosial Developers Private Limited in Santacruz East, Mumbai 400055, registered with MahaRERA as PR1180002502994. It was launched in March 2026. It has 46 units in 2 buildings: 44 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 28 are for sale, 15 are rehab units for existing members and 3 are the land-owner's share, not for sale.

Its registered possession date is March 2031, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

0 units booked out of 28 units for sale (0%).