Lotus Celestia, Versova
by Valuemart Real Estate Private Limited · Versova, Mumbai 400061 · Map
- Launched
- Mar 20264 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 0%Early stage
- Booked
- 146 of 15892% · 138 in Jul 2026
- Buildings
- 11.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 136
- 4 BHK
- 1
- 5+ BHK
- 19
- Other units
- 2
- Total units
- 158
- Buildings
- 1
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 136
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 5% | 0% | 0% | 146 | |
| 5% | 0% | 0% | 138 |
"–" means MahaRERA shows no figure for that update.
About this project
Lotus Celestia by Valuemart Real Estate Private Limited is a 158-unit SRA-sanctioned project in Versova, Mumbai 400061, launched in March 2026 with possession due in December 2030. 146 units booked out of total 158 units. Work on the concrete structure (RCC) has not started.
Read full summary
Lotus Celestia is an SRA-sanctioned project by Valuemart Real Estate Private Limited in Versova, Mumbai 400061, registered with MahaRERA as PR1180002503057. It was launched in March 2026. It has 158 units in 1 building: 156 homes (1, 4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation 5% complete, structure (RCC) not started, final finishes not started.
146 units booked out of total 158 units (92%). Since the July 2026 update, 8 more units have been booked.