Christina Apartment CHSL, Malad West
by U. K. Properties · Malad West, Mumbai 400064 · Map
- Launched
- Apr 20263 yrs 2 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 4 of 2218% · 20 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 22 units
Rehab20 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 30
- 3 BHK
- 6
- Other units
- 6
- Total units
- 42
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 4 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400064
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 5 mths |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | Jun 2029 | Mar 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 18% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Pratap Bhavan, Malad West
- Our Home Chsl, Malad West
- SHUBH MANGAL SRA CHS (Prop), Malad West
- Bhavana Residency, Malad West
- Poddar Highgarden, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pratap Bhavan | May 2026 | December 2028 | 0% | 2 units booked out of 12 units for sale |
| Our Home Chsl | July 2026 | September 2030 | 0% | 0 units booked out of 2 units for sale |
| SHUBH MANGAL SRA CHS (Prop) | July 2026 | April 2030 | 0% | 0 units booked out of 97 units for sale |
| Bhavana Residency | August 2026 | March 2030 | 0% | 0 units booked out of 5 units for sale |
| Poddar Highgarden | October 2026 | September 2029 | 0% | 0 units booked out of 39 units for sale |
About this project
Christina Apartment CHSL by U. K. Properties is a 42-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in April 2026 with possession due in June 2029. 4 units booked out of 22 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Christina Apartment CHSL is a BMC-sanctioned project by U. K. Properties in Malad West, Mumbai 400064, registered with MahaRERA as PR1180002600221. It was launched in April 2026. It has 42 units in 1 building: 36 homes (2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 22 are for sale and 20 are rehab units for existing members.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
4 units booked out of 22 units for sale (18%). Since the July 2026 update, 4 more units have been booked.