Platinum Stellar, Santacruz West

by Platinumcorp Elegant Residences Private Limited · Santacruz West, Mumbai 400054 · Map

Launched
Apr 20263 yrs 8 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
3 of 2811% · 11 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 28 units

Rehab11 units for existing members

Total 39 units. Rehab units are not for sale.

Project facts

3 BHK
20
4 BHK
19
Total units
39
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%3
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Jan 2029
Concrete structure (RCC)0%0%
Units booked (free sale)11%11%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Platinum Stellar by Platinumcorp Elegant Residences Private Limited is a 39-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in April 2026 with possession due in December 2029. 3 units booked out of 28 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Platinum Stellar is an SRA-sanctioned project by Platinumcorp Elegant Residences Private Limited in Santacruz West, Mumbai 400054, registered with MahaRERA as PR1180002600268. It was launched in April 2026. It has 39 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 39 units, 28 are for sale and 11 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

3 units booked out of 28 units for sale (11%). Since the July 2026 update, 3 more units have been booked.