Lakeview Villas, Juhu

by Agarwal Holdings Pvt Ltd · Juhu, Mumbai 400049 · Map

Launched
May 20262 yrs 9 mths promised
Possession (MahaRERA)
Feb 2029Not extended
Concrete structure
100%Nearing possession
Booked
17 of 2959%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
4 BHK
11
Total units
29
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Reserved units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%17
100%100%0%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400049

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs 9 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Feb 2029May 2030
Concrete structure (RCC)100%0%
Units booked59%27%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Lakeview Villas by Agarwal Holdings Pvt Ltd is a 29-unit BMC-sanctioned project in Juhu, Mumbai 400049, launched in May 2026 with possession due in February 2029. 17 units booked out of total 29 units. The concrete structure (RCC) is complete.

Read full summary

Lakeview Villas is a BMC-sanctioned project by Agarwal Holdings Pvt Ltd in Juhu, Mumbai 400049, registered with MahaRERA as PR1180002600334. It was launched in May 2026. It has 29 units in 1 building, with 1 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is February 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

17 units booked out of total 29 units (59%).