Skip to main content

Tarun Yuvak Sangh Chsl, Borivali East

by Ossia developers · Borivali East, Mumbai 400066 · Map

Launched
May 20262 yrs 4 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
45%Mid-construction
Booked (free sale)
0 of 90% · 4 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 9 units

Rehab4 units for existing members

Total 13 units. Rehab units are not for sale.

Project facts

1 BHK
5
2 BHK
7
3 BHK
1
Total units
13
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 45%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs
Possession date extendedNo3 of 6
Possession date (MahaRERA)Sep 2028Nov 2029
Concrete structure (RCC)45%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Tarun Yuvak Sangh Chsl by Ossia developers is a 13-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in May 2026 with possession due in September 2028. 0 units booked out of 9 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Tarun Yuvak Sangh Chsl is a BMC-sanctioned project by Ossia developers in Borivali East, Mumbai 400066, registered with MahaRERA as PR1180002600368. It was launched in May 2026. It has 13 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 13 units, 9 are for sale and 4 are rehab units for existing members.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

0 units booked out of 9 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 45%.