Stuvi Residency, Goregaon West
by Stuvi Reality LLP · Goregaon West, Mumbai 400062 · Map
- Launched
- May 20261 yr 7 mths originally promised
- Possession (MahaRERA)
- Apr 2030Extended by 2 yrs 4 mths
- Concrete structure
- 10%Mid-construction
- Booked (free sale)
- 0 of 40% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 4 units
Rehab8 units for existing members
Total 12 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- Total units
- 12
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 4
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 10% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Stuvi Residency by Stuvi Reality LLP is a 12-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in May 2026 with possession due in April 2030. 0 units booked out of 4 units for sale. The concrete structure (RCC) is 10% complete.
Read full summary
Stuvi Residency is a BMC-sanctioned project by Stuvi Reality LLP in Goregaon West, Mumbai 400062, registered with MahaRERA as PR1180002600462. It was launched in May 2026. It has 12 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 12 units, 4 are for sale and 8 are rehab units for existing members.
Its registered possession date is April 2030, extended by 2 years 4 months from the original December 2027. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.
0 units booked out of 4 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 10% and the possession date has moved from December 2027 to April 2030.