Aditi Co Operative Housing Society Ltd, Borivali West
by R N Associates · Borivali West, Mumbai 400092 · Map
- Launched
- May 20262 yrs 10 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 1 of 128% · 12 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 12 units
Rehab12 units for existing members
Total 24 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 8
- 2 BHK
- 16
- Total units
- 24
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 6 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Mar 2029 | Jan 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 8% | 2% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Ruchi Chsl, Borivali West
- Hansa Residency, Borivali West
- Siddharth Borivali CHSL, Borivali West
- Vardhaman, Borivali West
- Hill View, Borivali West
- Mahavir Dynasty, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ruchi Chsl | May 2026 | March 2030 | 23% | 0 units booked out of 16 units for sale |
| Hansa Residency | June 2026 | December 2028 | 0% | 2 units booked out of 27 units for sale |
| Siddharth Borivali CHSL | June 2026 | June 2030 | 0% | 6 units booked out of 32 units for sale |
| Vardhaman | March 2026 | December 2028 | 35% | 0 units booked out of 7 units for sale |
| Hill View | July 2026 | April 2031 | 0% | 0 units booked out of 16 units for sale |
| Mahavir Dynasty | September 2026 | December 2029 | 0% | 1 unit booked out of 27 units for sale |
About this project
Aditi Co Operative Housing Society Ltd by R N Associates is a 24-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in May 2026 with possession due in March 2029. 1 unit booked out of 12 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Aditi Co Operative Housing Society Ltd is a BMC-sanctioned project by R N Associates in Borivali West, Mumbai 400092, registered with MahaRERA as PR1180002600516. It was launched in May 2026. It has 24 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 12 are for sale and 12 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
1 unit booked out of 12 units for sale (8%). Since the July 2026 update, 1 more unit has been booked.