Om Sahil Co-operative Housing Society Limited, Jogeshwari East
by Dipti Home Makers Pvt Ltd · Jogeshwari East, Mumbai 400060 · Map
- Launched
- May 20264 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 20%Mid-construction
- Booked (free sale)
- 0 of 60% · 10 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 6 units
Rehab10 units for existing members
Total 16 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 11
- 3 BHK
- 5
- Total units
- 16
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 20% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400060
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 7 mths | 2 yrs 8 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2030 | Dec 2028 |
| Concrete structure (RCC) | 20% | 0% |
| Units booked (free sale) | 0% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Shree Samarth Chs Ltd, Jogeshwari East
- Sky Sixty, Jogeshwari East
- Kalpataru Verbina, Jogeshwari East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Samarth Chs Ltd | April 2026 | December 2028 | 0% | 0 units booked out of 6 units for sale |
| Sky Sixty | June 2026 | December 2028 | 0% | 0 units booked out of total 18 units |
| Kalpataru Verbina | December 2025 | December 2029 | 0% | 5 units booked out of total 18 units |
About this project
Om Sahil Co-operative Housing Society Limited by Dipti Home Makers Pvt Ltd is a 16-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in May 2026 with possession due in December 2030. 0 units booked out of 6 units for sale. The concrete structure (RCC) is 20% complete.
Read full summary
Om Sahil Co-operative Housing Society Limited is a BMC-sanctioned project by Dipti Home Makers Pvt Ltd in Jogeshwari East, Mumbai 400060, registered with MahaRERA as PR1180002600573. It was launched in May 2026. It has 16 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 6 are for sale and 10 are rehab units for existing members.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.
0 units booked out of 6 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 20%.