Sujata Nivas, Bandra West
by Roswalt Realty Private Limited · Bandra West, Mumbai 400050 · Map
- Launched
- Jun 20264 yrs 4 mths promised
- Possession (MahaRERA)
- Oct 2030Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 1 of 303% · 26 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 30 units
Rehab26 units for existing members
Total 56 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 17
- 3 BHK
- 16
- 4 BHK
- 1
- Other units
- 22
- Total units
- 56
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 30
- Rehab units
- 26
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400050
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 4 yrs 2 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Oct 2030 | Aug 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 3% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Marina Vista, Bandra West
- Kripa Jewel, Bandra West
- Icon Opus 50, Bandra West
- Narang Castella, Bandra West
- Paradigm Green Acrres, Bandra West
- Oceanic, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Marina Vista | June 2026 | June 2031 | 0% | 0 units booked out of 19 units for sale |
| Kripa Jewel | July 2026 | April 2030 | 0% | 3 units booked out of 19 units for sale |
| Icon Opus 50 | July 2026 | July 2028 | 0% | 0 units booked out of 14 units for sale |
| Narang Castella | May 2026 | March 2032 | 0% | 0 units booked out of 24 units for sale |
| Paradigm Green Acrres | April 2026 | December 2029 | 0% | 0 units booked out of 11 units for sale |
| Oceanic | April 2026 | December 2030 | 0% | 3 units booked out of 15 units for sale |
About this project
Sujata Nivas by Roswalt Realty Private Limited is a 56-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in June 2026 with possession due in October 2030. 1 unit booked out of 30 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Sujata Nivas is an SRA-sanctioned project by Roswalt Realty Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002600645. It was launched in June 2026. It has 56 units in 1 building: 34 homes (2, 3 and 4 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 56 units, 30 are for sale and 26 are rehab units for existing members.
Its registered possession date is October 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
1 unit booked out of 30 units for sale (3%). Since the July 2026 update, 1 more unit has been booked.