DEM Oak, Borivali West

by Dem Cornerstone Private Limited · Borivali West, Mumbai 400091 · Map

Launched
Jun 20263 yrs 10 mths promised
Possession (MahaRERA)
Apr 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 1860% · 49 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 186 units

Rehab49 units for existing members

Total 235 units. Rehab units are not for sale.

Project facts

1 BHK
94
2 BHK
118
3 BHK
11
4 BHK
1
5+ BHK
1
Other units
10
Total units
235
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
186
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

DEM Oak by Dem Cornerstone Private Limited is a 235-unit MHADA-sanctioned project in Borivali West, Mumbai 400091, launched in June 2026 with possession due in April 2030. 0 units booked out of 186 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

DEM Oak is a MHADA-sanctioned project by Dem Cornerstone Private Limited in Borivali West, Mumbai 400091, registered with MahaRERA as PR1180002600835. It was launched in June 2026. It has 235 units in 2 buildings: 225 homes (1, 2, 3, 4 and 5+ BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 235 units, 186 are for sale and 49 are rehab units for existing members.

Its registered possession date is April 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 186 units for sale (0%).