Kalpataru Hrushikesh, Jogeshwari West

by Kalpataru Townships Private Limited · Jogeshwari West, Mumbai 400102 · Map

Launched
Jun 20266 yrs promised
Possession (MahaRERA)
Jun 2032Not extended
Concrete structure
0%Early stage
Booked (free sale)
33 of 16520% · 178 rehab units
Buildings
44.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale33 booked out of 165 units

Rehab178 units for existing members

Total 343 units. Rehab units are not for sale.

Project facts

3 BHK
109
4 BHK
22
5+ BHK
31
Other units
181
Total units
343
Buildings
4
Land
4.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
165
Rehab units
178

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%33
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400102

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs4 yrs 5 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Jun 2032Dec 2030
Concrete structure (RCC)0%0%
Units booked (free sale)20%1%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Kalpataru Hrushikesh by Kalpataru Townships Private Limited is a 343-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in June 2026 with possession due in June 2032. 33 units booked out of 165 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Kalpataru Hrushikesh is a BMC-sanctioned project by Kalpataru Townships Private Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as PR1180002600863. It was launched in June 2026. It has 343 units in 4 buildings: 162 homes (3, 4 and 5+ BHK) and 181 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 343 units, 165 are for sale and 178 are rehab units for existing members.

Its registered possession date is June 2032, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

33 units booked out of 165 units for sale (20%). Since the July 2026 update, 33 more units have been booked.

Kalpataru's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA42
Total units across these projects6,678
Completed without extending the possession date19
Completed after an extension8
Lapsed0
Under construction15
Possession date extended on the builder's application9
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Kalpataru projects225 (21 of 42 projects)