Raya - Verdue, Chembur

by F. A. Builders & Developers LLP · Chembur, Mumbai 400074 · Map

Launched
Jan 20261 yr 9 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 2 yrs 2 mths
Concrete structure
0%Early stage
Booked
11 of 8313% · 0 in Jul 2026
Buildings
12.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
2
3 BHK
78
Other units
2
Total units
83
Buildings
1
Land
2.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%11
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Raya - Verdue by F. A. Builders & Developers LLP is an 83-unit SRA-sanctioned project in Chembur, Mumbai 400074, launched in January 2026 with possession due in December 2029. 11 units booked out of total 83 units. Work on the concrete structure (RCC) has not started.

Read full summary

Raya - Verdue is an SRA-sanctioned project by F. A. Builders & Developers LLP in Chembur, Mumbai 400074, registered with MahaRERA as PR1181012502128. It was launched in January 2026. It has 83 units in 1 building: 81 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 2 years 2 months from the original October 2027. Construction: excavation complete, structure (RCC) not started, final finishes not started.

11 units booked out of total 83 units (13%). Since the July 2026 update, 11 more units have been booked.