Raya - Verdue, Chembur
by F. A. Builders & Developers LLP · Chembur, Mumbai 400074 · Map
- Launched
- Jan 20261 yr 9 mths originally promised
- Possession (MahaRERA)
- Dec 2029Extended by 2 yrs 2 mths
- Concrete structure
- 0%Early stage
- Booked
- 11 of 8313% · 0 in Jul 2026
- Buildings
- 12.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 2
- 3 BHK
- 78
- Other units
- 2
- Total units
- 83
- Buildings
- 1
- Land
- 2.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 11 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Raya - Verdue by F. A. Builders & Developers LLP is an 83-unit SRA-sanctioned project in Chembur, Mumbai 400074, launched in January 2026 with possession due in December 2029. 11 units booked out of total 83 units. Work on the concrete structure (RCC) has not started.
Read full summary
Raya - Verdue is an SRA-sanctioned project by F. A. Builders & Developers LLP in Chembur, Mumbai 400074, registered with MahaRERA as PR1181012502128. It was launched in January 2026. It has 83 units in 1 building: 81 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, extended by 2 years 2 months from the original October 2027. Construction: excavation complete, structure (RCC) not started, final finishes not started.
11 units booked out of total 83 units (13%). Since the July 2026 update, 11 more units have been booked.