Golfshire B, Chembur

by Vensco Projects LLP · Chembur, Mumbai 400071 · Map

Launched
Feb 20264 yrs 10 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked
3 of 744% · 2 in Jul 2026
Buildings
12.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
72
4 BHK
2
Total units
74
Buildings
1
Land
2.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%3
0%0%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400071

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths3 yrs 8 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2030Jan 2030
Concrete structure (RCC)0%0%
Units booked4%0%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Golfshire B by Vensco Projects LLP is a 74-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in February 2026 with possession due in December 2030. 3 units booked out of total 74 units. Work on the concrete structure (RCC) has not started.

Read full summary

Golfshire B is an SRA-sanctioned project by Vensco Projects LLP in Chembur, Mumbai 400071, registered with MahaRERA as PR1181012502283. It was launched in February 2026. It has 74 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

3 units booked out of total 74 units (4%). Since the July 2026 update, 1 more unit has been booked.