Nest Wing B, Andheri East

by M86 Residency Private Limited · Andheri East, Mumbai 400093 · Map

Launched
Feb 20264 yrs 1 mth promised
Possession (MahaRERA)
Mar 2030Not extended
Concrete structure
14%Mid-construction
Booked
0 of 520%
Buildings
11.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
52
Total units
52
Buildings
1
Land
1.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)14%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 14%Oct 2026: Concrete structure (RCC) 14%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 14%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%14%0%0
100%14%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nest Wing B by M86 Residency Private Limited is a 52-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in February 2026 with possession due in March 2030. 0 units booked out of total 52 units. The concrete structure (RCC) is 14% complete.

Read full summary

Nest Wing B is an SRA-sanctioned project by M86 Residency Private Limited in Andheri East, Mumbai 400093, registered with MahaRERA as PR1181012502504. It was launched in February 2026. It has 52 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 14% complete, final finishes not started.

0 units booked out of total 52 units (0%).