Emerald - Dotom Isle, Kandivali West

by M/S. Dotom Real Estate · Kandivali West, Mumbai 400067 · Map

Launched
Jan 20264 yrs 11 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
112 of 40228% · 6 rehab units
Buildings
26.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale112 booked out of 402 units

Rehab6 units for existing members

Total 408 units. Rehab units are not for sale.

Project facts

1 BHK
215
2 BHK
183
3 BHK
3
Other units
7
Total units
408
Buildings
2
Land
6.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
402
Rehab units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%112
100%0%0%71
0%0%0%56

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400067

Projects with 200–900 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths3 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2030Jun 2029
Concrete structure (RCC)0%0%
Units booked (free sale)28%28%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Emerald - Dotom Isle by M/S. Dotom Real Estate is a 408-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in January 2026 with possession due in December 2030. 112 units booked out of 402 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Emerald - Dotom Isle is an SRA-sanctioned project by M/S. Dotom Real Estate in Kandivali West, Mumbai 400067, registered with MahaRERA as PR1183032502034. It was launched in January 2026. It has 408 units in 2 buildings: 401 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 408 units, 402 are for sale and 6 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

112 units booked out of 402 units for sale (28%). Since the July 2026 update, 41 more units have been booked.