Yashada projects in Pune
Every MahaRERA project by Yashada in the 59 areas FlatNama covers, registered 2017–2026.
- Registered
- 112017–2026
- Under construction
- 6
- Completed
- 33 without extending
- Complaints
- 4across 4 of 11
Track record
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 11 |
|---|---|
| Completed without extending the possession date | 3 |
| Completed after an extension, or lapsed | 2 |
| Under construction | 6 |
| Possession date extended by the builder | 0 |
| Typical time from launch to 100% structure | 2 years 8 months |
| Complaints on MahaRERA, all Yashada projects | 4 (4 of 11 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Ravet (2) · Mamurdi (1) · Pimple Nilakh (1) · Moshi (1) · Baner (1) · Punawale (1)
Under construction (6)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Yashada Dreamsong | Mamurdi | Mid-construction | December 2029 | 42 of 314 booked (13%) |
| Yashada Earthsong | Ravet | Early stage | December 2033 | 206 of 599 booked (34%) |
| Yashada EVO Residences PH - I | Punawale | Early stage | December 2034 | |
| Yashada Jubilee Hills | Baner | Finishing stage | December 2026 | 81 of 83 booked (98%) |
| Yashada Supreme | Moshi | Finishing stage | December 2027 | 1,059 of 1,093 booked (97%) |
| Yashada Windsong | Ravet | Finishing stage | December 2026 | 404 of 413 booked (98%) |
Completed (3)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Epic Phase 1 | ||||
| Yashada Florenza | ||||
| Yashada Splendid Park |
Lapsed (2)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Epic Phase 2 | Pimple Nilakh | Mid-construction | December 2025 | 56 of 77 booked (73%) |
| Epic Phase 3 |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.