Atmosphere projects in Mumbai
MahaRERA projects by Atmosphere registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 6 |
|---|---|
| Total units across these projects | 2,401 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 2 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 4 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 5 years 3 months |
| MahaRERA complaints (filed by or against the builder), all Atmosphere projects | 22 (3 of 6 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Mulund West (2) · Chembur (2) · Bandra West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Atmosphere · 2 phases | Mulund West | Nearing possession | Dec 2026 | – |
| Atmosphere O2 Tower-G | Chembur | Nearing possession | December 2028 | 353 units booked out of total 435 units |
| Marina Vista | Bandra West | Early stage | June 2031 | 0 units booked out of 19 units for sale |
| O2 Hi-Street | Mulund West | Early stage | August 2027 | 1 unit booked out of total 4 units |
Completed
| Project | Village | Status |
|---|---|---|
| The Gateway | Chembur | Completed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us