Atmosphere, Mulund West
by Atmosphere Realty Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Jul 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 60.5 acres
- MahaRERA complaints
- 21Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 2
- 1 BHK
- 7
- 2 BHK
- 999
- 3 BHK
- 537
- Other units
- 11
- Total units
- 1,556
- Buildings
- 6
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 21
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Atmosphere Phase 1 Completed | P51800001243 | 721 | 100% | – | |
| Atmosphere O2 Nearing possession | P51800019950 | 824 | 100% | 95% |
Show updates by phase
Atmosphere Phase 1 (P51800001243)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 719 |
"–" means MahaRERA shows no figure for that update.
Atmosphere O2 (P51800019950)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 67% | 788 | |
| 100% | 100% | 67% | 788 | |
| 100% | 100% | 67% | 780 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400080
Projects with 700–3,100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 5 yrs 6 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Jan 2027 |
| Concrete structure (RCC) | 100% | 97% |
| MahaRERA complaints (filed by or against the builder) | 21 | 24 |
The 3 projects
- Montana, Mulund West
- Piramal Revanta, Mulund West
- The Sanctuary, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Montana | July 2017 | Dec 2026 | 100% | – |
| Piramal Revanta | August 2017 | Nov 2028 – Jul 2030 | 97% | – |
| The Sanctuary | September 2017 | Jan 2027 – Mar 2027 | 94% | 891 units booked out of total 1,797 units |
About this project
Atmosphere by Atmosphere Realty Pvt Ltd is a 1,556-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 2 phases, with possession due in December 2026. The concrete structure (RCC) is complete.
Read full summary
Atmosphere is a BMC-sanctioned project by Atmosphere Realty Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as 2 phases (P51800001243, P51800019950). The first phase was launched in July 2017. Together the phases have 1,556 units in 6 buildings: 1,545 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 82% complete. Both phases have their structure complete.
Atmosphere's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 6 |
|---|---|
| Total units across these projects | 2,401 |
| Completed without extending the possession date | 2 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 4 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 5 years 3 months |
| MahaRERA complaints (filed by or against the builder), all Atmosphere projects | 22 (3 of 6 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.