Kanakia projects in Mumbai

MahaRERA projects by Kanakia registered 2017–2026 in Mumbai.

Projects registered with MahaRERA17
Total units across these projects4,603
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date13
Completed after an extension2
Lapsed0
Under construction2
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Kanakia projects80 (13 of 17 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Andheri East (3) · Powai (3) · Khar West (1) · Versova (1) · Malad East (1) · Kandivali West (1) · Bhandup East (1) · Mahim (1) · Borivali West (1)

Under construction

ProjectVillageStagePossessionBooked
Kanakia Future City · 3 phasesPowaiNearing possessionSep 2026–
Kanakia Privaasa Tower 1 & 2Borivali WestEarly stageJune 20310 units booked out of 277 units for sale
Completed
ProjectVillageStatus
Kanakia Future CityPowaiCompleted
Kanakia HollywoodVersovaCompleted
Kanakia LevelsMalad EastCompleted
Kanakia MiamiMahimCompleted
Kanakia ParisKhar WestCompleted
Kanakia RainforestAndheri EastCompleted
Kanakia SevensAndheri EastCompleted
Kanakia Silicon Valley FPowaiCompleted
Kanakia WallstreetAndheri EastCompleted
Kanakia ZenworldBhandup EastCompleted
Sarla AvenueKandivali WestCompleted

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.