Kanakia Future City, Powai

by Kanakia Future Realty Private Limited · Powai, Mumbai 400076 · Map

Launched
Oct 2018First of 3 phases
Possession (MahaRERA)
Sep 2026Not extended
Concrete structure
100%Weighted across 3 phases
Booked
–
Buildings
30.6 acres
MahaRERA complaints
7Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
303
3 BHK
219
5+ BHK
1
Total units
524
Buildings
3
Land
0.6 acres
Phases
3
MahaRERA complaints
7

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kanakia Future City A
Completed
P51800018007186100%–
Kanakia Future City C
Completed
P51800018008171100%–
Kanakia Future City E
Ready to move
P51800034748167100%90%
Show updates by phase

Kanakia Future City A (P51800018007)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%–
100%100%65%–
100%100%65%122

"–" means MahaRERA shows no figure for that update.

Kanakia Future City C (P51800018008)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%–
100%100%60%–
100%100%60%136

"–" means MahaRERA shows no figure for that update.

Kanakia Future City E (P51800034748)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%150
100%100%95%–
100%100%95%–
100%100%95%150

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services73%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 73%Dec 2025: Final finishes 73%Jul 2026: Final finishes 73%Oct 2026: Final finishes 73%Excavation 100%Concrete structure (RCC) 100%Final finishes 73%

How to read construction stages

About this project

Kanakia Future City by Kanakia Future Realty Private Limited is a 524-unit project in Powai, Mumbai 400076, registered with MahaRERA in 3 phases, with possession due in September 2026. The concrete structure (RCC) is complete.

Read full summary

Kanakia Future City is a project by Kanakia Future Realty Private Limited in Powai, Mumbai 400076, registered with MahaRERA as 3 phases (P51800018007, P51800018008, P51800034748). The first phase was launched in October 2018. Together the phases have 524 units in 3 buildings, with 1, 2, 3 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 2 are completed and 1 is active.

The registered possession date is September 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 73% complete. All 3 phases have their structure complete.

Kanakia's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA17
Total units across these projects4,603
Completed without extending the possession date13
Completed after an extension2
Lapsed0
Under construction2
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Kanakia projects80 (13 of 17 projects)

See all Kanakia projects →